AnsweredAAbutPierQ&A #1865122004-06-22 05:09 · Views 15

Please check the number of rebars

철근상세를 검토하다 기초철근 B1~B4번 철근의 갯수가 이상하여 글 올립니다. 대략 10개정도 빠져있는거 같은데...검토좀 해주세요. (A1쪽 입니다)

Answer

안녕하세요. 한길아이티입니다. 수정하였습니다. 금일자 패치에 반영하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2222026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3742026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3132026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1942026-09-18
AnsweredAAbutPier#268451Changing bearing location922026-09-18
AnsweredAAbutPier#268445Main rebar placement3082026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2382026-09-17
AnsweredAAbutPier#268422Question about pier2772026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2662026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask