Abutment input

슬래브제원에서 포장40mm, 슬래브850mm로 제대로 입력하였는데 교대입력란에 PH값이 자동으로 생성되는 과정에서 (40+850+400)-550(슈위치)X0.005=1287mm의 높이가 나와야 하는데. 1258mm가 나옵니다. 도저히 에러를 찾지 못하여 올립니다. 감사합니다. [개인정보]:[개인정보]

Answer

안녕하세요. 한길아이티입니다. (40+850+400) 에서 400은 슈의 높이로 생각이 됩니다. 하지만 입력상으로 슈의 높이는 371로 되어 있습니다. 그래서 400-371 = 29 mm 차이가 발생하고 있습니다. 또한 1258 + 29 = 1287 로 수치가 일치하는것을 알 수 있습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2222026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3762026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3132026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1942026-09-18
AnsweredAAbutPier#268451Changing bearing location922026-09-18
AnsweredAAbutPier#268445Main rebar placement3102026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2402026-09-17
AnsweredAAbutPier#268422Question about pier2772026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2682026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask