전화로 문의 들였던 내용입니다. 경사 교대 일반도 (평면도)에서 접속슬래브 시작선이 직선으로 안되고 약간 경사가져서 출력이 되서 접속슬래브 배근도에서도 길이 차이가 나게됩니다. 검토바랍니다.. (파일첨부) 이메일은 [개인정보] 로 보내주세여
Answer
안녕하세요. 한길아이티입니다. 교대의 한쪽에 날개벽이 없는 경우에 오차가 발생하였습니다. 수정하였고 금일자 패치에 적용하도록 하겠습니다. 패치는 금일 21:00에 올라갈 예정입니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 222 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 384 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 313 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 194 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 329 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 244 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 277 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 227 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |