About the quantity calculation report

일반수량산출서 확인 부탁드립니다. 수평력, 높이 혼합되어 출력

Answer

안녕하세요. 한길아이티입니다. 1) 교량받침의 집계에서 슈제원이 참조되지 않은 받침에서 집계상의 오류가 있었습니다. 2) 두부보의 수직면,경사면등의 분류는 실적수량을 기준으로 산정하였을 때의 분류방법 입니다. 교각1에서 수직면이 나온 것이 잘못된 출력이었습니다. 1),2)의 사항은 수정하였습니다. 금일자 패치에 반영하도록 하겠습니다. 다른 사항이 있으시면 게시판에 남기시거나 전화주시기바랍니다. ([개인정보],[한길 담당자]) ps) 전화번호가 등록되어있지않아 연락을 못했습니다. 개인정보를 수정하여 주시면 감사하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1822026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2222026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3892026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2062026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2272026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3142026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2762026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1952026-09-18
AnsweredAAbutPier#268451Changing bearing location942026-09-18
AnsweredAAbutPier#268445Main rebar placement3312026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4152026-09-17
AnsweredAAbutPier#268433Pier alignment center1902026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2442026-09-17
AnsweredAAbutPier#268422Question about pier2782026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2692026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars4022026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2292026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1822026-09-16
Sign in to ask