Program crash
안녕하세요 오늘아침에 apier패치파일을 받아서 업데이트를 하였는데도 프로그램이 다운되는게 계속되고 있습니다. 다른부분에서는 쭉 진행이 되다가 교각의 주철근을 입력하는부분에서 다운이 되고 있는데 살펴봐주시면 감사하겠습니다. 파일을 첨부하겠습니다.
Answer
안녕하세요. 한길아이티입니다. 확인한 바 이상이 없습니다. 그런데 데이타의 값들이 설정이 되어있지 않습니다. 각 교각마다 주철근 입력등에서 권고안을 수행하셔야 합니다. 답변을 보시고 궁금한 점이 있으시면 전화주시기 바랍니다. ([개인정보],[한길 담당자]) 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 182 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 222 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 390 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 206 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 228 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 315 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 276 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 195 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 331 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 415 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 190 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 244 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 278 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 402 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 230 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 182 | 2026-09-16 |