Questions on P.F bridge design
P.F교량 적용시 교대 슈받침 콘크리트 하단까지의 E.L 산출에 대한 질문사항입니다. 예를 들어서 상부 높이가 1.2M이고 콘크리트교면포장 0.04M 그리고 슈받침전체높이 0.4M라고 할시 상부 E.L 9.000이라고 하면 9.000-1.2-0.04-0.4 =E.L 7.36이어야 되는데 [개인정보]에서는 7.35가 나오네요 아마도 P.C빔 관련해서 슬래브와 빔접합부의 몰탈높이를 그대로 적용을 한것 같은데 P.F교는 합성교로서 이렇게 적용하는게 맞는지 의문이 가네요 답변부탁드릴게요 그럼 오늘도 [개인정보]의 발전을 위하여...
Answer
안녕하세요. 한길아이티입니다. EL 부분은 슬래브 부분의 입력에 따라 변할 수 있습니다. apr 파일을 첨부해주시면 검토해 보겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 183 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 223 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 258 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 204 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 390 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 207 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 228 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 315 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 276 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 195 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 332 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 416 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 190 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 244 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 279 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 403 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 230 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 182 | 2026-09-16 |