AnsweredAAbutPierQ&A #1839052003-12-11 02:32 · Views 61

Question about approach slab

기 수정된 (-) 접속슬래브 적용에 오류가 있는것같습니다. 첨부된 파일의 종점([개인정보])방향 접속슬래브 확인해 주십시오. 감사합니다.

Answer

안녕하세요. 한길아이티입니다. 수정하였습니다. 금일자 패치에 적용하겠습니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1832026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2232026-09-29
AnsweredAAbutPier#268520Pier seismic check2582026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2042026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3912026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2082026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2282026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3162026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2762026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1952026-09-18
AnsweredAAbutPier#268451Changing bearing location942026-09-18
AnsweredAAbutPier#268445Main rebar placement3322026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4172026-09-17
AnsweredAAbutPier#268433Pier alignment center1902026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2442026-09-17
AnsweredAAbutPier#268422Question about pier2792026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2692026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars4032026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2302026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1822026-09-16
Sign in to ask