AnsweredAAbutPierQ&A #1836962003-11-27 19:00 · Views 53

Problem creating the reinforcement drawing

1. 수고 많으십니다. 2. 교대, 교각의 배근도의 철근번호 및 철근직경의 표시 부분이 도곽 밖에 표시되어 따로 따로 입니다. 3. 환경설정의 문제인것 같은데 도와주세요. 4. 참고로 처음에는 출력이 제대로 잘 되었는데 수정하던 중에 이렇게 되었읍니다.

Answer

안녕하세요. 한길아이티입니다. 추가적으로 보내주신 파일에서 일반도 입력에서 약간 입력상의 오류가 발견되었습니다. 이 점에 대해서는 저희에게 직접 연락 바랍니다. ([전화] : [한길 담당자]) 감사합니다. 안녕하세요. 한길아이티입니다. 실시간 업데이트를 한번더 해주시기 바랍니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1832026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2232026-09-29
AnsweredAAbutPier#268520Pier seismic check2582026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2042026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3912026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2082026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2292026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3172026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2762026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1952026-09-18
AnsweredAAbutPier#268451Changing bearing location942026-09-18
AnsweredAAbutPier#268445Main rebar placement3322026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4182026-09-17
AnsweredAAbutPier#268433Pier alignment center1902026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2442026-09-17
AnsweredAAbutPier#268422Question about pier2792026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2692026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars4042026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2302026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1822026-09-16