Follow-up on post no. 5370
안녕하세요. 글번호 5370에 대한 답을 전화로 잘받았습니다. 그런데 그중에서 이상한점이 있어서 올립니다. 6. 하부구조 교각설계시 상부반력에서 활하중의 편재하반력 적용시 최대편심 모멘트가 발생하는 차선 재하를 고려하여야 할것으로 사료됨. brx 파일루 import하면 자동으로 계산을 한다구 했는데 확인해보니깐 편재하를 3차선으루 g1최대와 g2 최대를 적용하더라구요. 그경우보다는 2차선재하나 1차선재하가 더 불리 하다구 생각됩니다 파일 첨부하오니 검토바랍니다. 수고하세요..
Answer
안녕하세요. 한길아이티입니다. T형교각 일 경우에 좀더 고려해야될 문제가 있었습니다. 개선방안을 적용하도록 하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 183 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 223 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 259 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 204 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 391 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 209 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 229 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 317 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 277 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 195 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 332 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 418 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 191 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 245 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 279 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 404 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 232 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 182 | 2026-09-16 |