AnsweredAAbutPierQ&A #1828922003-10-10 22:49 · Views 52

Wing wall shear reinforcement

최소전단철근 검토에 대해...

Answer

안녕하세요. 한길아이티입니다. Vc값을 확인하시면 최소전단철근량에서 N.G를 확인하실 수 있습니다. 나머지 사항은 전화로 말씀드렸습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1832026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2232026-09-29
AnsweredAAbutPier#268520Pier seismic check2592026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2052026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3912026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2102026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2292026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3182026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2772026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1952026-09-18
AnsweredAAbutPier#268451Changing bearing location942026-09-18
AnsweredAAbutPier#268445Main rebar placement3332026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4192026-09-17
AnsweredAAbutPier#268433Pier alignment center1912026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2452026-09-17
AnsweredAAbutPier#268422Question about pier2792026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2692026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars4062026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2322026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1822026-09-16