Compression rebar CTC 125 not applied to abutment heel
안녕하세요.. [교대 주철근 입력]에서 교대 뒷굽 하면 압축철근 CTC를 125로 하였는데 도면(004쪽)에 적용이 되지 않습니다. 확인해 주시길 바랍니다.
Answer
안녕하세요. 한길아이티입니다. 철근제원에서 B4철근의 제원을 B3과 동일하게 입력하시면 됩니다. 자동으로 설정되어야 하는 부분이므로 수정하여 패치에 반영하도록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 183 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 223 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 259 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 207 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 392 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 212 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 231 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 320 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 277 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 195 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 333 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 419 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 192 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 245 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 279 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 407 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 233 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 183 | 2026-09-16 |