Abutment reinforcement drawing problem
교대 배근도가 잘못나옵니다. 철근 넘버링도 안나오고 그러네요.. 날개벽 전단철근도 아직도 누락이구요..? 파일을 보내드립니다.. 이상이 있는지 알려주세요..
Answer
안녕하세요. 한길아이티입니다. 1) A4의 우측날개벽의 철근넘버링 출력오류는 수정하였습니다. 패치에 반영하도록 하겠습니다. 패치는 금일(8월25일) 18:00에 올라갈 예정입니다. 번거로우시겠지만 [교대입력]-[철근제원]에서 A4-우측날개벽TAB에서 [적용]버튼을 한번 눌러주시기바랍니다. 2) 날개벽의 전단철근관련사항은 현재 작업중에 있습니다. 금주내에 적용하도록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 183 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 223 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 260 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 207 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 392 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 213 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 231 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 320 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 278 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 195 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 94 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 333 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 419 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 192 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 245 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 279 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 269 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 408 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 233 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 183 | 2026-09-16 |