AnsweredAAbutPierQ&A #1814502003-07-11 04:58 · Views 69

Main rebar input issue

파일이 주철근 입력에서부터 계속 다운이 됩니다. 어찌 할수가 없네요!

Answer

안녕하세요. 한길아이티입니다. 작업에 불편을 드려서 죄송합니다. 수정한 파일을 첨부합니다. 패치파일을 받으셔서 실행하시면 됩니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1832026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2232026-09-29
AnsweredAAbutPier#268520Pier seismic check2632026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2082026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3952026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2132026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2312026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3202026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2792026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1962026-09-18
AnsweredAAbutPier#268451Changing bearing location942026-09-18
AnsweredAAbutPier#268445Main rebar placement3332026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4192026-09-17
AnsweredAAbutPier#268433Pier alignment center1922026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2452026-09-17
AnsweredAAbutPier#268422Question about pier2792026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2732026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars4092026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2332026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1842026-09-16