a2흉벽 주철근량을 계산이 되지않아서 계속 n.g가 납니다 검토바랍니다
Follow-up2007-12-11 14:32
확인을해보니 흉벽배면2이케 체크가 안되있어서 그렇더군요 허나 흉벽배면2를 체크하면 흉벽배면1철근과 흉벽배면2철근이 겹칩니다 확인하여주십시요 >>a2흉벽 주철근량을 계산이 되지않아서 계속 n.g가 납니다 검토바랍니다
Answer2007-12-11 14:50
안녕하세요. 한길아이티입니다. 질의 하신 사항은 검토진행중이며, 완료시 [개인정보]에서 답변하겠습니다. 감사합니다.
Answer2007-12-11 16:39
안녕하세요. 한길아이티입니다. 하단 브라켓이 없는 교대의 경우 교대입력-주철근 배근에서 흉벽배면1에 입력된 철근으로 설계검토가 이루어지도록 수정하여 금일중에 패치하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 178 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 213 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 242 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 190 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 330 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 215 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 300 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 263 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 189 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 86 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 259 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 397 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 217 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 244 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 232 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 382 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 217 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 170 | 2026-09-16 |