접속슬래브 상세도에서 DB2 철근의 위치가 표준도와 다른게 나옵니다. 도로공사 표준도(2003.5)의 4.091 도면을 보면 D2 철근은 접속슬래브 바닥이 아닌 중간에 위치합니다. 상세도 변경 부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 질의하신 부분을 수정하여 금일중 패치하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1782026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2132026-09-29
AnsweredAAbutPier#268520Pier seismic check2422026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1902026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3302026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2152026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3012026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2642026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1892026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2612026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis3982026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2192026-09-17
AnsweredAAbutPier#268422Question about pier2462026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2322026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3822026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2182026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1702026-09-16
Sign in to ask