AnsweredAAbutPierQ&A #2079502007-11-06 09:59 · Views 38

Berm treatment for front embankment

수고하십니다 교대 입력의 소단 제원에서 소단처리를 없애려면 어떻게 해야 하나요 날개벽 뒤에 본선 옹벽이 설치되는 곳의 압성토를 삭제하려고 합니다

Answer

안녕하세요. 한길아이티입니다. 올려드리는 파일 참조하시면 됩니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1782026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2152026-09-29
AnsweredAAbutPier#268520Pier seismic check2442026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1912026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3312026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2152026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3032026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2662026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1892026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2622026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4012026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2212026-09-17
AnsweredAAbutPier#268422Question about pier2472026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2342026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3822026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2192026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1712026-09-16