Plan view dimension error
수고하십니다 보내드린 첨부화일의 교대 입력의 평면도 제원에서 치수선의 구조물 위치와 슈위치 등이 맞지 않네요 확인바람니다
Answer
안녕하세요. 한길아이티입니다. 선단브라켓 적용시 평면도 출력부분에 오류가 있었습니다. 수정작업중이며 완료시 답변하겠습니다. 감사합니다. 안녕하세요. 한길아이티입니다. 답변이 늦어 죄송합니다. 선단브라켓부분을 수정하여 오전중으로 패치하겠습니다. 불편을 드려 죄송합니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 179 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 215 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 244 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 191 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 331 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 215 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 303 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 267 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 189 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 262 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 401 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 221 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 247 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 234 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 383 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 219 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 171 | 2026-09-16 |