AnsweredAAbutPierQ&A #2076922007-10-26 19:30 · Views 32

Pier bearing seat reinforcement detailing

교각 교좌면 받침 배근도 화면이 나오지를 않아 배근을 못했습니다. 무엇이 잘못인지 수정해주세요.. -[개인정보]-

Answer2007-10-26 10:47

안녕하세요. 한길아이티입니다. 교좌면 제원의 H2값 50을 입력누락하셔서 그렇습니다. H2에 입력하시면 철근배근이 가능하게 됩니다. 감사합니다.

Follow-up2007-10-26 11:45

네 해결됐네요...

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1792026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2152026-09-29
AnsweredAAbutPier#268520Pier seismic check2442026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1912026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3312026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2152026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3032026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2682026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1892026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2622026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4012026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2212026-09-17
AnsweredAAbutPier#268422Question about pier2472026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2342026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3832026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2192026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1712026-09-16
Sign in to ask