Error designing a bridge with two superstructure types
상부형식이 섞인 교량(psc+precom)을 설계중 입니다. psc부분은 brx파일을 로드 시켜서 하고, precom부분은 상부하중을 받아서 하부를 설계하려고 하는데 "지가구성입력","지점각도입력" 부분부터 오류가 생깁니다. 다음으로 넘어가서 종점부분 A2단면은 생성도 안됩니다. 급한 일이라서 빠른 답변 주시면 감사 하겠습니다... 종평면도 파일도 함께 첨부합니다.
Answer
안녕하세요. 한길아이티입니다. 교량 받침 좌표 편집 부분에서 새로 입력하시는 부분에 대한 좌표를 입력하지 않으셨습니다. 그 부분에 좌표를 입력하시면 됩니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 217 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 245 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 334 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 268 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 190 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 263 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 402 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 223 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 247 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 235 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 389 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 220 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |