교대입력 > 날개벽제원 > 소단제원입력 에서 앞성토가 있는것으로 입력하였으나, 일반수량산출시 교대보호블럭 수량이 산출되지 않아 질문합니다.

Answer

안녕하세요. 한길아이티입니다. 교대설계환경-수량선택사항-교대보호블럭설치을 선택하셔야지 수량에 반영됩니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1802026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2182026-09-29
AnsweredAAbutPier#268520Pier seismic check2482026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1922026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3352026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2162026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3062026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2692026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1912026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2642026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4042026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2252026-09-17
AnsweredAAbutPier#268422Question about pier2492026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2372026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3912026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2222026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1752026-09-16
Sign in to ask