On the bearing seat surface
안녕하세요... 계속 질문을 올려서 아실 것 같은데 거더가 2개에서 3개로 변하면서 연결부 교각(15)의 교좌면 받침배치가 뒤쪽 거더의 중심을 따라서 배치가 됩니다. 사실 앞쪽 거더의 중심이 선형의 중심이므로 교각의 중심이 되어야 하는데 뒤쪽 거더의 중심을 따라 갑니다. 첨부 파일 올립니다. 그럼 빠른 답변 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 두부보제원입력에서 편측이동에 대한 수치입력을 하시면 됩니다. 180입력하면 전열기준의 중심으로 들어가게 됩니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 269 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 227 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 251 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 240 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |