안녕하세요 되메우기 수량에서 뒷채움량을 제하는데 뒷채움 수량에서 구해놓은 값과 제할때 뒷채움량과 차이가 나는 이유가 먼가요? 검토부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 뒤채움수량은 계획고에 의한값이면 되메우기시 뒷채움수량은 원지반을 기준으로 터파기를 하므로 원지반까지의 뒷채움수량입니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1802026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2182026-09-29
AnsweredAAbutPier#268520Pier seismic check2482026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1922026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3352026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2162026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3062026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2692026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1912026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2712026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4042026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2292026-09-17
AnsweredAAbutPier#268422Question about pier2522026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2432026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3912026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2222026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1752026-09-16
Sign in to ask