기둥의 띠철근 배치에서 설계검토를 하게되면 사용철근량계산에서 텍스트가 깨져서 출력이 됩니다. 파일을 첨부하니 검토바랍니다.

Answer

안녕하세요. 한길아이티입니다. 교각기둥부주철근배치의 2단에 있는 H25을 없애주시면 해결됩니다. 2단철근이 있는것으로 판단되서 생기는 것입니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1802026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2182026-09-29
AnsweredAAbutPier#268520Pier seismic check2482026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K1922026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3352026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check1982026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2162026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3062026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2692026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1912026-09-18
AnsweredAAbutPier#268451Changing bearing location872026-09-18
AnsweredAAbutPier#268445Main rebar placement2712026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4042026-09-17
AnsweredAAbutPier#268433Pier alignment center1862026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2292026-09-17
AnsweredAAbutPier#268422Question about pier2522026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2432026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3912026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2222026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1752026-09-16
Sign in to ask