About braking load and collision load
수고 많으십니다.. 도로교인데 제동하중을 고려하고 싶은데 어디에서 고려해야 하나요?? 또 교각 설계조건에서 유목 선박,기타부유물의 중량을 넣게 되어있는데 실제 계산상 고려가 되지 않는것 같아서.. 답변 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 도로교의 제동하중은 아직 고려되지 않습니다. AAbutPier의 차기버전에서 고려될 예정으로 작업중에 있습니다. 유목 선박,기타부유물 하중에 대해서는 이렇게 검토하신 파일(apr)을 첨부해 주시면 상세시 검토하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 279 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 233 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 260 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 246 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |