About pile cap beam reinforcement detailing
두부보 배근에서 보강철근이 주철근 2단과 3단에 배치가 잘안돼고 있습니다. input data를 첨부합니다. 확인부탁드립니다. tel)[개인정보]
Answer
안녕하세요. 한길아이티입니다. 답변이 늦어 죄송합니다. 말씀하신 사항은 확인하였으며 보완하여 금일자 패치에 적용하도록 하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 289 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 234 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 262 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 249 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |