Abutment foundation design
교대 3)기초설계 2.하중조합에서 하중증가계수의 적용이 어떻게 이루어 졌는지요? 수직력, 수평력, 모멘트에 적용시킨 하중증가계수가 모두 다르게 적용되어 있는것 같은데 엑셀에 수식을 첨부하여 주시면 고맙겠습니다.
Answer
안녕하세요. 한길아이티입니다. 하중증가계수는 하중조합 테이블 하단에 표시면 표기되어 있습니다. 해당 하중계수에 적용된 번호를 적용하여 확인하시면 됩니다. 검토한 엑쎌파일을 첨부하니 참조하시기 바랍니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 289 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 234 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 262 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 249 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |