Shear rebar in wing wall reinforcement drawing
단면의 제약으로 인해 날개벽 두께가 500으로 제한되었습니다 C단면 전단검토시 최소전단철근이 들어가게 되어있는데 0.5d 간격 규정으로 인해 전단철근 간격을 125로 입력하였는데 배근도에서는 다르게 나오더군요 검토 부탁드립니다
Answer
안녕하세요. 한길아이티입니다. 날개벽의 기초접합부(B,C구간)에 대한 전단입력은 B구간과 C구간이 중첩되어 적용되는 값이 B구간으로 되어 있습니다. B,C구간의 전단을 다르게 적용을 하지는 않으며 B구간의 입력값이 적용됩니다. 해당 입력값을 B구간에 입력하신 후에 확인하시면 됩니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 87 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 289 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 234 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 262 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 249 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |