Earthwork quantity report looks wrong, please check
안녕하세요.. 다름이 아니라...Apier 상에서는 분명 보령방향과 서천방향에 대한 토공산출근거 나오는데 엑셀로 출력하면 나오지가 않아요.. 일반수량이나..다른 것은 다 같이 나오는데..이유를 모르겠어요.. 제가 옵션을 잘 못 한 것인지..아무리 확인해도..이해가 되지가 않네요.. 확인 좀 부탁드립니다..(조금 급하니..빨리 검토 좀 해주세요)
Answer
안녕하세요. 한길아이티입니다. 교대명이 같은 경우에 수량산출서가 출력되지 않을 수 있습니다. A1,A2,A1,A2로 되어 있는 교대명을 변경하신 후에 확인하시면 됩니다. 위와 같은 경우에 출력이 되지않는 부분은 추가로 검토하도록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 88 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 291 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 234 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 263 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 251 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |