ELEVATION calculation
업데이트 후 엘리베이션 산출이 좀 이상합니다. 첨부파일 ELEVATION 산출근거도 왜관방향 A1 ①번을 보면 94.204(거더EL)-1.750(거더높이)-0.169(교량받침높이)-0.050(MORTAR두께)-0.181(BLOCK두께)=92.054(교좌면EL)가 나와야 하나 92.055가 나오네요. 확인바랍니다. 기존에 높이10.000m로 되어있던 교대가 9.999m로 나오네요
Answer
안녕하세요. 한길아이티입니다. 반올림이 합하여 질 경우 소수점 자리 반올림에서 오류가 있었습니다. 이전에는 이 반올림을 조정하였는데, 더 정확하게 한다는 것이 실제 설계와는 맞지않았습니다. 수정하였습니다. 19시 패치에 올리겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 180 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 218 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 248 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 192 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 198 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 216 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 306 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 269 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 191 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 88 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 291 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 404 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 186 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 234 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 264 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 251 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 391 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 222 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 175 | 2026-09-16 |