Coping rebar display error
코핑부평면도를보면 코핑주철근2,3단을 보여주기위해 반원으로 파서 보여주는부분이있습니다. C1,C3,C5는 1cycle로써 끊지않고 코핑전폭을 다갑니다. 그리고 C2,C4,C6 은 2cycle로써 중앙부에서는 끊어지는데, 여기서 C4,C6철근이 보여지는 부분을 보면 C3,C5철근이 없습니다. 또한 C8철근은 중앙부 하면 2cycle 철근으로 기둥부에서는 끊어지는데 C7철근과 겹쳐나오고 철근길이도 2000~7320인데 그냥 7320이 아닌지...제가 수정한 Cad 화일을 같이첨부했습니다. 확인부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 말씀하신 사항 모두 확인하였습니다. 수정해서 패치에 반영하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 220 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 253 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 335 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 223 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 309 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 272 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 193 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 88 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 292 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 408 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 188 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 235 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 266 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 254 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 396 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 225 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |