Check of horizontal rebar quantity in abutment foundation

현재 프로그램상 적용 수평철근 검토 전면벽과 저판에는 인장철근의 20% 이상의 배력철근을 두어야 한다.라고 있는데 이는 옹벽 기준에 있는것이 적용이 되에 있는것 같아 검토바랍니다. 연직벽 : 0.0025 BH (전면, 배면 각각 1/2) 교대흉벽 : 0.0025 BH (전면, 배면 각각 1/2) 기초 및 라멘 : 0.002 BH 인장,압축 각각1/2) 적용하는것이 타당하다고 봅니다.

Answer

안녕하세요. 한길아이티입니다. si단위일때는 2005 도로교설계기준에 맞게 적용되어 있으나, cgs일때는 아직 적용되지 않았습니다. 수정하여 패치에 적용하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2212026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3382026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3122026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1932026-09-18
AnsweredAAbutPier#268451Changing bearing location882026-09-18
AnsweredAAbutPier#268445Main rebar placement2942026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2362026-09-17
AnsweredAAbutPier#268422Question about pier2682026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2542026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask