When outputting structural drawings
구조도 출력시 예기치 않은 line이 생성이 되네요. 철근 번호에서의 오류인것 같습니다.(11,12,1415,16번 도면) 검토 부탁드립니다. 감사합니다.
Answer
안녕하세요. 한길아이티입니다. 확인한 바 이상이 없는 것 같습니다. 그리고 기초 및 벽체에 2단을 배치하였는데 주철근만 입력이 되었고 배력철근의 2단입력이 누락되었습니다. 입력데이타를 확인하여 주시기 바랍니다. 확인은 현재 패치로 하였으며 다시 확인하여 주시고 다른 사항이시면 게시판에 남겨 주시거나 전화주시기 바랍니다. ([개인정보], [한길 담당자]) 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 221 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 342 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 312 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 193 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 88 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 295 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 236 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 269 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 254 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |