AnsweredAAbutPierQ&A #1910092005-03-15 10:32 · Views 56

Please make a correction

말뚝과 확대기초의 결합부검토시 철근의 정착길이(Lo)값 비교할때 부등호값이 잘못 입력되어 있습니다. 수정부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 수정하였습니다. 금일자 패치에 적용하도록 하겠습니다. 상세한 지적에 감사드립니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2212026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3462026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3122026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1932026-09-18
AnsweredAAbutPier#268451Changing bearing location882026-09-18
AnsweredAAbutPier#268445Main rebar placement2972026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2372026-09-17
AnsweredAAbutPier#268422Question about pier2702026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2562026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask