AnsweredAAbutPierQ&A #1901342005-01-12 01:08 · Views 66

Load calculation for pier structural analysis

본 교량은 25/35/25의 단경간 연속교량이며 활하중은 EL18입니다. 첫번째 25/35의 중간에 고정단이 2개 배치된형태입니다. 하중산정시 1. 고정단교갹의 장대레일하중 산정 2. 차량횡하중 재하시 좌우측 지간이 다른경우 2번째 바퀴를 지간 중앙에 재하하는 것이 최대로 사료됨 3. 시동/제동하중 산정시 25와35의 60m 지간에 재하되는 차량의 총 바퀴수는 25에7개 35에 8개로 총 15입니다. 출력된 엑셀파일을 동봉하오니 검토하시고 답변 부탁드립니다

Answer

안녕하세요. 한길아이티입니다. 오류사항을 확인하였습니다. 수정후 패치에 반영하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2212026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3492026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3122026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1932026-09-18
AnsweredAAbutPier#268451Changing bearing location882026-09-18
AnsweredAAbutPier#268445Main rebar placement2992026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2372026-09-17
AnsweredAAbutPier#268422Question about pier2712026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2572026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask