첨부한 티형 교각대로 단면입력이 가능한지요?
Answer
안녕하세요. 한길아이티입니다. 다른 제원들은 모두 입력이 가능한 사항이나 측면도에 표기된 기둥연단에서의 1200의 치수는 현제 입력이 지원되지 않습니다. (기초상단의 경사부시점과 기둥연단사이의 거리) 이 부분은 현재 작업중이며 수요일자 패치에 적용할 예정입니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 221 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 354 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 312 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 193 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 88 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 299 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 237 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 271 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 258 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |