AnsweredAAbutPierQ&A #1892702004-11-22 23:59 · Views 31

Please review

보도육교 설계중인데 A2만 데이타가 필요한거라서 A2만 출력하려고 합니다.(도면, 수량, 계산) 그런데 도면이 제대로 나오지 않습니다. 날개벽은 수평으로 편 상태입니다. 바쁘시겠지만 검토 부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 날개벽의 D구간입력이 누락되었습니다. 수정한 파일을 첨부하니 참조하시기 바랍니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2212026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3542026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3122026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1932026-09-18
AnsweredAAbutPier#268451Changing bearing location892026-09-18
AnsweredAAbutPier#268445Main rebar placement2992026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2372026-09-17
AnsweredAAbutPier#268422Question about pier2712026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2592026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask