업무에 노고가 많으십니다~ 교각해석을 SAP2000 자동실행을 하면 "경고"메세지가 뜹니다. 두부보에 강역구간을 설정하였습니다. 두부보에 강역구간을 설정하지 않으면 "경고"메세지가 뜨지 않습니다. SAP에서의 문제인데 제가 아무리 봐도 "경고"가 뜨는 이유를 모르겠어서 올려봅니다. 수고하세요~ _(__)_ 파일첨부합니다~
Answer
안녕하세요. 한길아이티입니다. 전화상으로 말씀드렸습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 221 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 354 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 312 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 193 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 89 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 299 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 237 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 271 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 259 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |