About the calculation report
사용철근량/요구철근량 ====>사용률(*.***) 로 나오는 부분에서요 요구철근량이 단순히 계산된 값이 사용되는데... 요구철근량은 최소철근비와 4/3 요구철근량 이상 사용하게 되어있습니다. 따라서 사용률은 사용철근량/요구 적용 철근량으로 바꾸어야 할것같습니다. 실제보다 사용률이 많이 나와서 지적이 나오네요..
Answer
안녕하세요. 한길아이티입니다. 철근사용률은 단순히 필요철근량에 대한 사용철근량을 표기하였습니다. 사용률이라는 문구의 해석상 말씀하신 바와같이 할 수도 있을 것같습니다. 이 부분은 검토 후 보완하도록 하겠습니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 221 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 359 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 312 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 193 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 89 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 304 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 237 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 274 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 260 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |