Structural calculation report cannot be output

첨부한 파일에서 교각2는 계산서 출력이 되는데 교각1이 출력이 안됩니다. 기초부 철근배근에서 다운 되는데요.. 검토바랍니다.

Answer

안녕하세요. 한길아이티입니다. 입력메뉴에서의 오류는 수정하였습니다. 계산서 출력은 확인한 바 이상이 없습니다. 수정내용은 금일자 패치에 적용하도록 하겠습니다. 감사합니다.

Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#268560Question about the calculation report1812026-09-29
AnsweredAAbutPier#268548Tendon force when placing tendons in the pier cap2212026-09-29
AnsweredAAbutPier#268520Pier seismic check2572026-09-23
AnsweredAAbutPier#268509Transverse reinforcement factor, K2022026-09-22
AnsweredAAbutPier#268492Girder positions in slab dimensions3622026-09-21
AnsweredAAbutPier#268483Transverse pile member forces are "0" in pier pile foundation check2032026-09-21
AnsweredAAbutPier#268482Top and bottom rebar detailing error in pier foundation STM2242026-09-21
AnsweredAAbutPier#268476Question about slab dimensions3122026-09-19
AnsweredAAbutPier#268470Settlement and bearing capacity2742026-09-18
AnsweredAAbutPier#268462Superstructure wind load in the calculation report1932026-09-18
AnsweredAAbutPier#268451Changing bearing location892026-09-18
AnsweredAAbutPier#268445Main rebar placement3052026-09-17
AnsweredAAbutPier#268438Modeling error in seismic analysis4112026-09-17
AnsweredAAbutPier#268433Pier alignment center1892026-09-17
AnsweredAAbutPier#268431Please check the design ground surface displacement2372026-09-17
AnsweredAAbutPier#268422Question about pier2752026-09-17
AnsweredAAbutPier#268416Wprov calculation in the structural calculation report2602026-09-17
AnsweredAAbutPier#268402Increasing the number of column main rebars3982026-09-16
AnsweredAAbutPier#268392Question about cast-in-place piles2262026-09-16
AnsweredAAbutPier#268387Error when entering reinforcing rebar1802026-09-16
Sign in to ask