When entering abutment parapet rebar
수고하십니다........ 교대 흉벽부분 철근입력에 관해서 질문 드리겠습니다. 계산시에는 흉벽의 상단과 하단이 나뉘어 계산이 가능하지만 주철근 입력시 구분이 되어 있지 않아 혹시 구분하여 주철근을 입력할수 있는지 빠른 답변 부탁드립니다..... 제가 알기로는 옵션에는 그러한 기능이 없는걸로 알고 있습니다만.....
Answer
안녕하세요. 한길아이티입니다. 벽체부배근 입력에서 "흉벽상단부 철근 ㄷ자 철근상세 적용"을 하시면 상단부의 배면철근이 흉벽전면철근에 입력한 직경과 같이 설정이 됩니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 221 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 363 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 312 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 194 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 90 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 305 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 237 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 275 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 261 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |