내진에서 모델링이 새성오류가 뜨네요. 화일 첨부 하오니 확인 바랍니다.
Answer
안녕하세요. 한길아이티입니다. 내진해석 단면입력에서 빔단면에 대한 3축방향의 단면2차모멘트가 누락되었으며, 가로보 단면에 대한 특성치 및 중량이 누락되어 있습니다. 입력 후 확인을 하시면 이상이 없습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #268560 | Question about the calculation report | 181 | 2026-09-29 |
| Answered | AAbutPier | #268548 | Tendon force when placing tendons in the pier cap | 222 | 2026-09-29 |
| Answered | AAbutPier | #268520 | Pier seismic check | 257 | 2026-09-23 |
| Answered | AAbutPier | #268509 | Transverse reinforcement factor, K | 202 | 2026-09-22 |
| Answered | AAbutPier | #268492 | Girder positions in slab dimensions | 366 | 2026-09-21 |
| Answered | AAbutPier | #268483 | Transverse pile member forces are "0" in pier pile foundation check | 203 | 2026-09-21 |
| Answered | AAbutPier | #268482 | Top and bottom rebar detailing error in pier foundation STM | 224 | 2026-09-21 |
| Answered | AAbutPier | #268476 | Question about slab dimensions | 313 | 2026-09-19 |
| Answered | AAbutPier | #268470 | Settlement and bearing capacity | 274 | 2026-09-18 |
| Answered | AAbutPier | #268462 | Superstructure wind load in the calculation report | 194 | 2026-09-18 |
| Answered | AAbutPier | #268451 | Changing bearing location | 90 | 2026-09-18 |
| Answered | AAbutPier | #268445 | Main rebar placement | 305 | 2026-09-17 |
| Answered | AAbutPier | #268438 | Modeling error in seismic analysis | 411 | 2026-09-17 |
| Answered | AAbutPier | #268433 | Pier alignment center | 189 | 2026-09-17 |
| Answered | AAbutPier | #268431 | Please check the design ground surface displacement | 237 | 2026-09-17 |
| Answered | AAbutPier | #268422 | Question about pier | 275 | 2026-09-17 |
| Answered | AAbutPier | #268416 | Wprov calculation in the structural calculation report | 262 | 2026-09-17 |
| Answered | AAbutPier | #268402 | Increasing the number of column main rebars | 398 | 2026-09-16 |
| Answered | AAbutPier | #268392 | Question about cast-in-place piles | 226 | 2026-09-16 |
| Answered | AAbutPier | #268387 | Error when entering reinforcing rebar | 180 | 2026-09-16 |