Applying continuous welded rail load
1. 장대레일하중 재하시 시점에서 종점 재하되어 있으나, 종점에서 시점으로 재하가 되지 않고 있습니다. 양뱡향 재하가 되어야 할것 같은데 확인 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 장대레일 하중 양방향 제하 추가되었습니다. Aupdate 통하여 최신버전 update 후 사용하시기 바랍니다. 감사합니다.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | ACulvert | #226364 | Inquiry about vertical earth pressure increase factor 2 | 47 | 2005-07-29 |
| Answered | ACulvert | #226363 | Inquiry about culvert vertical earth pressure increase factor | 56 | 2005-07-29 |
| Answered | ACulvert | #226362 | Cannot change wall distribution rebar | 50 | 2005-07-29 |
| Answered | ACulvert | #226360 | Why does this happen? | 36 | 2005-07-29 |
| Answered | ACulvert | #226358 | Wing wall reinforcement detailing | 32 | 2005-07-29 |
| Answered | ACulvert | #226356 | Drawings are not generated | 30 | 2005-07-29 |
| Answered | ACulvert | #226355 | In basic data input | 71 | 2005-07-28 |
| Answered | ACulvert | #226353 | Allowable bearing capacity check | 85 | 2005-07-28 |
| Answered | ACulvert | #226351 | Error message during buoyancy check | 36 | 2005-07-28 |
| Answered | ACulvert | #226349 | Formula issue in pile check (seismic) | 40 | 2005-07-27 |
| Answered | ACulvert | #226347 | Please check | 36 | 2005-07-27 |
| Answered | ACulvert | #226345 | Suggested improvements | 91 | 2005-07-26 |
| Answered | ACulvert | #226339 | Bearing capacity check for channel box | 46 | 2005-07-22 |
| Answered | ACulvert | #226342 | Bracket | 40 | 2005-07-22 |
| Answered | ACulvert | #226340 | Distribution rebar in approach slab | 39 | 2005-07-22 |
| Answered | ACulvert | #226337 | Design lane width | 77 | 2005-07-22 |
| Answered | ACulvert | #226335 | Bearing capacity check for channel box | 52 | 2005-07-22 |
| Answered | ACulvert | #226333 | About the basic data input | 48 | 2005-07-19 |
| Answered | ACulvert | #226331 | Please check | 31 | 2005-07-18 |
| Answered | ACulvert | #226329 | Lap splices in the 2nd cycle | 31 | 2005-07-18 |