AnsweredAAbutPierQ&A #1286002014-08-26 15:20 · Views 227

Styrofoam quantity for separated abutment?

안녕하세요... 교대을 선형, 선형반대반방향으로 분리 설계을 하는데요.. 일반수량 산출시 분리교대 사이에 들어가는 스티로폼 10mm 아이탬 산출여부란이 있는지요?? 빠른답변 부탁드립니다.. 감사합니다

Answer

안녕하세요. 한길아이티입니다. 질의하신 사항은 수량산출-수량산출옵션 선택-교대탭의 인접교대에서 옵션으로 제공되고 있으며 공제적용시 스티로폴의 설치와 거푸집의 공제로 적용됩니다. 인접해있는 구조물을 자동으로 교려하고 있지는 않으므로 교대의 설치방향을 고려하여 적용하시면 됩니다. 감사합니다.

Attached images 1

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#197593Please fix error shown in the wall reinforcement detailing tab112006-02-09
AnsweredAAbutPier#197577Please review seismic check72006-02-09
AnsweredAAbutPier#197575Error in wind load modeling52006-02-09
AnsweredAAbutPier#197589Please improve bearing seat dimension input162006-02-08
AnsweredAAbutPier#197580Applying one layer instead of two for reinforcing bars under bridge bearings112006-02-08
AnsweredAAbutPier#197567When up and down lines have different start points102006-02-08
AnsweredAAbutPier#197550In foundation settings262006-02-07
AnsweredAAbutPier#197549Wing wall reinforcement drawing452006-02-07
AnsweredAAbutPier#197548Feature request252006-02-07
AnsweredAAbutPier#197556Structural drawings per pier72006-02-07
AnsweredAAbutPier#197555Superstructure load not applied at bridge bearings112006-02-07
AnsweredAAbutPier#197554Calculated EL values look wrong102006-02-07
AnsweredAAbutPier#197539Wing wall check282006-02-06
AnsweredAAbutPier#197538Fonts are not displayed222006-02-06
AnsweredAAbutPier#197536Questions on automatic girder placement and more352006-02-06
AnsweredAAbutPier#197523ALine seems to be missing from the APier CD202006-02-06
AnsweredAAbutPier#197518Entering separate alignments302006-02-06
AnsweredAAbutPier#197516Seismic analysis error222006-02-05
AnsweredAAbutPier#197515Longitudinal step at P6 superstructure type change point is not applied282006-02-04
AnsweredAAbutPier#197514Can variable sections be applied to the top and bottom of a T-shaped pier?442006-02-03
Sign in to ask