AnsweredAAbutPierQ&A #1272702014-06-26 00:00 · Views 188

After entering horizontal alignment coordinates

평면선형을 그냥 심플하게 하고 작업할때는 교각 정보가 다 잘나왔었는데요 평면선형 좌표 정보를 넣고 작업을 하다보면 교각 단면도 제원에서 P1번만 제대로 나오고 나머지 교각에 대해서는 나오지 않습니다. 이유가 뭔지 모르겠네요 R3은 평면선형 넣기 전이고 R4는 평면선형 넣은 후입니다.

Answer

안녕하세요. 한길아이티입니다. 선형적용후 정상적으로 진행되지 않아 위치적용이 잘 되지 않은 것 같습니다. R3파일에서 선형적용후 전체적으로 진행시에는 정상 적용되는 것으로 확인되나 R4에서 작업하시려면 교좌면 단차에서 받침위치가 상당히 틀어져 있기때문에 [권고안]으로 초기화후 진행하시면 정상 진행가능할 것으로 생각됩니다. 감사합니다.

Attached images 1

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#196189Cross tie rebar quantity error142005-11-18
AnsweredAAbutPier#196184Distance from parapet to shoe center282005-11-18
AnsweredAAbutPier#196181Seismic pile reactions in pier foundation design with cast-in-place piles392005-11-18
AnsweredAAbutPier#196170Column design for a sway (unbraced) structure502005-11-18
AnsweredAAbutPier#196183Pile load test quantity292005-11-18
AnsweredAAbutPier#196182Coefficient of horizontal subgrade reaction312005-11-18
AnsweredAAbutPier#196179When changing rebar details382005-11-18
AnsweredAAbutPier#196174Changing main rebar to two layers652005-11-18
AnsweredAAbutPier#196161Temperature load calculation for pier at expansion joint seems wrong902005-11-18
AnsweredAAbutPier#196158Drawing generation532005-11-18
AnsweredAAbutPier#196155Pier bearing seat location mismatch352005-11-18
AnsweredAAbutPier#196152Follow-up to phone inquiry682005-11-18
AnsweredAAbutPier#196150About the stability index632005-11-18
AnsweredAAbutPier#196149Shoe tonnage is entered incorrectly892005-11-18
AnsweredAAbutPier#196142Additional question on 18970642005-11-18
AnsweredAAbutPier#196140About the left wing wall reinforcement drawing of the abutment712005-11-18
AnsweredAAbutPier#196129Spread footing thickness check472005-11-17
AnsweredAAbutPier#196163Rounding the bottom of the coping end112005-11-17
AnsweredAAbutPier#196135Number of bearings per girder702005-11-17
AnsweredAAbutPier#196121Cast-in-place pile rebar ratio592005-11-17