Skip to content
AnsweredAAbutPierQ&A #1256642014-03-27 18:56 · Views 183

Approach slab quantity missing

접속슬래브 수량이 집계가 안됩니다

Answer

안녕하세요. 한길아이티입니다. 수량산출옵션 - 교대탭의 기타항목에서 '수량집계에 접속/완충 슬래브 포함' 이 적용안함으로 설정되어 있습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#194386About shear rebar calculation for columns..302005-09-03
AnsweredAAbutPier#194384Wing wall and parapet reinforcing rebar252005-09-03
AnsweredAAbutPier#194379Entering step rebar in the coping572005-09-03
AnsweredAAbutPier#194368Seismic horizontal force is excessively large372005-09-02
AnsweredAAbutPier#194373Design conditions?342005-09-02
AnsweredAAbutPier#194358Abutment wing wall section thickness transition zone402005-09-02
AnsweredAAbutPier#194354Seismic analysis392005-09-01
AnsweredAAbutPier#194352About SAP2000 auto-run602005-09-01
AnsweredAAbutPier#194347In pier reinforcement drawing (1)402005-09-01
AnsweredAAbutPier#194343Cannot place cross beams412005-09-01
AnsweredAAbutPier#194341Bearing pedestal concrete and shoe location462005-09-01
AnsweredAAbutPier#194340Uploading the Osaek pedestrian overpass292005-09-01
AnsweredAAbutPier#194333Urgent question about earthwork262005-09-01
AnsweredAAbutPier#194332Pier section forces come out 1.5 times higher352005-09-01
AnsweredAAbutPier#194328Bridge bearings182005-08-31
AnsweredAAbutPier#194321Error during seismic analysis322005-08-31
AnsweredAAbutPier#194320Elevation looks wrong382005-08-31
AnsweredAAbutPier#194311Please review172005-08-31
AnsweredAAbutPier#194317Uploading Osaek pedestrian overpass data282005-08-31
AnsweredAAbutPier#194301Approach slab drawing outputs incorrectly232005-08-30
Sign in to ask