Reposting
질문을 잘못 이해하신거 같아서 다시 올립니다.... 첨부한 엑셀파일에 질문을 표시해 놓았습니다 검토 부탁드립니다.
Answer
안녕하세요. 한길아이티입니다. 답변이 늦어서 죄송합니다. 수량 산출부분에 대해서 수정하여 3시경에 패치하도록 하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #185037 | Why anchorage lengths differ for the same wing wall rebar | 44 | 2004-03-09 |
| Answered | AAbutPier | #185036 | Cast-in-place piles | 25 | 2004-03-09 |
| Answered | AAbutPier | #185021 | Quantity calculation | 25 | 2004-03-09 |
| Answered | AAbutPier | #185016 | Seismic analysis modeling | 25 | 2004-03-09 |
| Answered | AAbutPier | #185015 | Approach slab calculation report is missing | 28 | 2004-03-08 |
| Answered | AAbutPier | #185014 | Section input for seismic analysis | 45 | 2004-03-08 |
| Answered | AAbutPier | #185013 | Please check the cross beam | 20 | 2004-03-08 |
| Answered | AAbutPier | #185012 | Please check the cross beam | 25 | 2004-03-08 |
| Answered | AAbutPier | #185009 | Reactions when adding piles... | 22 | 2004-03-08 |
| Answered | AAbutPier | #185007 | Abutment wing wall | 17 | 2004-03-08 |
| Answered | AAbutPier | #185003 | About wing wall rebar | 10 | 2004-03-08 |
| Answered | AAbutPier | #185001 | Abutment report: shear check of foundation | 18 | 2004-03-07 |
| Answered | AAbutPier | #184999 | Check of pier (P1) reinforcement drawing | 24 | 2004-03-07 |
| Answered | AAbutPier | #184997 | The program crashes... | 24 | 2004-03-06 |
| Answered | AAbutPier | #184993 | Dimension line position of approach slab in abutment general drawing | 19 | 2004-03-06 |
| Answered | AAbutPier | #184991 | Cast-in-place pile drawings | 86 | 2004-03-06 |
| Answered | AAbutPier | #184989 | Please check number of horizontal rebars in wall body | 15 | 2004-03-06 |
| Answered | AAbutPier | #184988 | Cross-section layout of widened section... | 19 | 2004-03-05 |
| Answered | AAbutPier | #184984 | Approach slab missing from structural calculation report | 26 | 2004-03-05 |
| Answered | AAbutPier | #184986 | In abutment foundation settings input | 12 | 2004-03-05 |