AnsweredAAbutPierQ&A #1861612004-06-08 11:04 · Views 17

Subgrade reaction in foundation design

구조계산서-기초설계- 2.지반반력산정, 구조계산서-기초설계- 3-c.지반반력산정 에서 테이블안의 Qa, Qb 값이 표 상호간에 일치되지 않습니다. 검토 부탁드립니다.

Answer

안녕하세요. 한길아이티입니다. 지반반력산정에서의 Qa,Qb는 각각 벽체전면(앞굽),벽체배면(뒷굽)위치에서의 지반반력을 나타내고 있습니다. 설계단면력산정에서의 Qa,Qb는 전단검토위치와 모멘트검토위치에서의 반력을 나타 내고 있습니다. 같은 Qa,Qb를 사용하여 표현상의 혼란이 있는 것같습니다. 즉, 전단검토위치와 모멘트검토위치가 같으면 앞굽의 경우 지반반력산정에서의 Qa값을 모두 사용합니다. 확인해 보시고 이상이 있으시면 게시판에 남기시거나 전화주시기바랍니다. ([개인정보],[한길 담당자]) 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#186158When entering pier tie bars442004-06-08
AnsweredAAbutPier#186155Please correct EL. again152004-06-08
AnsweredAAbutPier#186161Subgrade reaction in foundation design · Currently viewing172004-06-08
AnsweredAAbutPier#186150Seismic analysis412004-06-08
AnsweredAAbutPier#186143Inquiry about bearing capacity check for pier mass foundation182004-06-08
AnsweredAAbutPier#186136Inquiry about design seismic force from seismic analysis292004-06-08
AnsweredAAbutPier#186132Uploading file52004-06-07
AnsweredAAbutPier#186126Horizontal force calculation for seismic load132004-06-07
AnsweredAAbutPier#186151Checking the hollow pier calculation report482004-06-07
AnsweredAAbutPier#186144Inquiry about cover at top of parapet wall112004-06-07
AnsweredAAbutPier#186120Cross ties in column tie bar reinforcement detailing262004-06-07
AnsweredAAbutPier#186117Request for review92004-06-07
AnsweredAAbutPier#186139Quantity calculation criteria122004-06-07
AnsweredAAbutPier#186135About the hollow pier calculation report312004-06-07
AnsweredAAbutPier#186131About the hollow pier structural calculation report192004-06-07
AnsweredAAbutPier#186129Error when generating drawings52004-06-07
AnsweredAAbutPier#186118Inquiry about pier drawings242004-06-07
AnsweredAAbutPier#186116About EL calculation132004-06-06
AnsweredAAbutPier#186115About the abutment general drawing242004-06-05
AnsweredAAbutPier#186113About the structural calculation report292004-06-05
Sign in to ask