Dimension line position of approach slab in abutment general drawing
교대 일반도 에서 접속슬래브의 치수선위치가 적절치 않아 일반도상에서 맞지 않습니다. 첨부한 파일과 출력된 도면을 확인하여 주시길 바랍니다.
Answer
안녕하세요. 한길아이티입니다. 슬래브의 끝단을 직각처리하는 경우 치수선표현이 잘못되는 부분은 수정하여 패치에 적용하도록 하겠습니다. 감사합니다.
Attachments on this post were deleted after the retention period (3 years after the last answer) and can no longer be downloaded. If you need the same material, please contact us.
More in this list
| Status | Product | No. | Title | Views | Date |
|---|---|---|---|---|---|
| Answered | AAbutPier | #185037 | Why anchorage lengths differ for the same wing wall rebar | 44 | 2004-03-09 |
| Answered | AAbutPier | #185036 | Cast-in-place piles | 25 | 2004-03-09 |
| Answered | AAbutPier | #185021 | Quantity calculation | 25 | 2004-03-09 |
| Answered | AAbutPier | #185016 | Seismic analysis modeling | 25 | 2004-03-09 |
| Answered | AAbutPier | #185015 | Approach slab calculation report is missing | 28 | 2004-03-08 |
| Answered | AAbutPier | #185014 | Section input for seismic analysis | 45 | 2004-03-08 |
| Answered | AAbutPier | #185013 | Please check the cross beam | 20 | 2004-03-08 |
| Answered | AAbutPier | #185012 | Please check the cross beam | 25 | 2004-03-08 |
| Answered | AAbutPier | #185009 | Reactions when adding piles... | 22 | 2004-03-08 |
| Answered | AAbutPier | #185007 | Abutment wing wall | 17 | 2004-03-08 |
| Answered | AAbutPier | #185003 | About wing wall rebar | 10 | 2004-03-08 |
| Answered | AAbutPier | #185001 | Abutment report: shear check of foundation | 18 | 2004-03-07 |
| Answered | AAbutPier | #184999 | Check of pier (P1) reinforcement drawing | 24 | 2004-03-07 |
| Answered | AAbutPier | #184997 | The program crashes... | 24 | 2004-03-06 |
| Answered | AAbutPier | #184993 | Dimension line position of approach slab in abutment general drawing · Currently viewing | 19 | 2004-03-06 |
| Answered | AAbutPier | #184991 | Cast-in-place pile drawings | 86 | 2004-03-06 |
| Answered | AAbutPier | #184989 | Please check number of horizontal rebars in wall body | 15 | 2004-03-06 |
| Answered | AAbutPier | #184988 | Cross-section layout of widened section... | 19 | 2004-03-05 |
| Answered | AAbutPier | #184984 | Approach slab missing from structural calculation report | 26 | 2004-03-05 |
| Answered | AAbutPier | #184986 | In abutment foundation settings input | 12 | 2004-03-05 |