AnsweredAAbutPierQ&A #1833812003-11-06 15:33 · Views 54

Please check

저희가 구한 하단 el과 a-pier에서 나온 el값이 약간 오차가 있어서 그렇습니다.

Answer

안녕하세요. 한길아이티입니다. 파일합치기때에 지간입력 오류 입니다. 지간을 590으로 수정하시면 됩니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredAAbutPier#183451Slab dimension input522003-11-12
AnsweredAAbutPier#183446About quantity calculation552003-11-11
AnsweredAAbutPier#183439Error during ASolver calculation462003-11-11
AnsweredAAbutPier#183435Pier column width differs from coping width (file attached)472003-11-11
AnsweredAAbutPier#183422Something odd in the approach slab quantities592003-11-10
AnsweredAAbutPier#183407Question about required main rebar area552003-11-10
AnsweredAAbutPier#183429Pier column width differs from coping width462003-11-10
AnsweredAAbutPier#183427Follow-up question542003-11-10
AnsweredAAbutPier#183426Pi-shaped rigid frame pier (separate foundations)542003-11-10
AnsweredAAbutPier#183425Requesting a reply542003-11-10
AnsweredAAbutPier#183411Section area error in wind load calculation702003-11-10
AnsweredAAbutPier#183409Abutment (bearing seat dimensions), Π-shaped pier (foundation settings)632003-11-10
AnsweredAAbutPier#183388Cross slope setting for individual abutment input552003-11-07
AnsweredAAbutPier#183374Please check462003-11-06
AnsweredAAbutPier#183372Question about quantity calculation512003-11-06
AnsweredAAbutPier#183381Please check · Currently viewing542003-11-06
AnsweredAAbutPier#183368Please review again742003-11-06
AnsweredAAbutPier#183365End-side abutment is placed reversed482003-11-06
AnsweredAAbutPier#183350Correction needed452003-11-05
AnsweredAAbutPier#183349Elevations do not match502003-11-05