Question in Korean (English title coming soon)

1. 편심거리가 (-)값이 나오면 유효접지면적에서 절대값을 적용하여 기초의 폭보다 적어야 하나 계산상 유효접지폭이 기초의 폭보다 크게나옴. (Be = B-2xe에서 e가 (-)이니까) 2. 활동에 대한 검토식은 도로설계기준(구 도로교 시방서)에서 구하는 방법과 콘크리트 설계기준(구 콘크리트 시방서) 에서 구하는 방법의 조건식이 서로 상이하지만 설계선택사항에서 도.설.기준을 선택하는 콘.설.기준을 선택하나 해석 결과에 적용되는식은 도.설.기준식을 적용하는것 같읍니다. 혹시 별도의 옵션이 있는가요?... (참고로 옹벽전용 무료SOFTWARE인 RAD([개인정보])를 참고하시면 되겠네요...)

Answer

안녕하세요. 한길아이티입니다. 1.편심거리는 수정후 업데이트 하겠습니다. 2.콘크리트 설계기준 적용시 콘크리트 기준식으로 적용되도록 추가하겠습니다. 감사합니다.

More in this list

StatusProductNo.TitleViewsDate
AnsweredACulvert#268543Pile calculation report3272026-09-28
AnsweredACulvert#268536Setting section changes in culvert1662026-09-28
AnsweredACulvert#268524Design check not performed at wall center2152026-09-27
AnsweredACulvert#268523Applying moving vehicle loads2322026-09-27
AnsweredACulvert#268522Question about pile layout2602026-09-23
AnsweredACulvert#268521Question about features1282026-09-23
AnsweredACulvert#268510Question about joint check in Excel report output1802026-09-22
AnsweredACulvert#268499Error in STM analysis of corner region1392026-09-22
AnsweredACulvert#268471Launching the culvert program592026-09-18
AnsweredACulvert#268442All lines are displayed as dashed lines, what should I do?1382026-09-17
AnsweredACulvert#268429Question about U-type underpass1262026-09-17
AnsweredACulvert#268424Load position when applying railway loads to an underpass2302026-09-17
AnsweredACulvert#268417Changing girder dimensions1472026-09-17
AnsweredACulvert#268396Incorrect section check location for horizontal rebar1732026-09-16
AnsweredACulvert#268376Question about segment settings for U-type retaining wall1852026-09-15
AnsweredACulvert#268343Question about culvert drawing output1262026-09-15
AnsweredACulvert#268337Inquiry about checking retaining-wall-type wing walls3002026-09-14
AnsweredACulvert#268330About drawing output1502026-09-14
AnsweredACulvert#268318Some blocks not displayed1352026-09-14
AnsweredACulvert#268317Tank load for surcharge and moving loads3342026-09-14
Sign in to ask